ВОРОНЕЖСКАЯ ТЭЦ

VORONEZH THERMAL POWER PLANT

On February 19, 2018, PROMFINSTROY JSC signed an agreement with PJSC Quadra— Generating Company to perform construction and installation work on the reconstruction of Voronezh CHP-1. A new department of capital construction of the enterprise was created in Voronezh.

Since March 2018, the specialists of the UKS of PROMFINSTROY JSC (Voronezh) have started implementing a project for the construction of a combined-cycle gas plant (CCGT-223 MW) at Voronezh CHP-1. As a result of the project, taking into account the plans for decommissioning technically and morally obsolete generating equipment, the efficiency of the thermal power plant as a whole has significantly increased.

The initial scope included work on the installation of on-site water supply and sewerage networks, the installation of foundations, installation of metal structures, architectural and construction solutions of the main building, as well as work on the installation of waste heat boilers with auxiliary equipment and nbsp;their piping. All works, including their intermediate stages, were completed within the agreed deadlines and approved by the customer.

Calculate the cost
Main characteristics
378,34 MW
Installed electric capacity (including CCGT-223: 240.34 MW)
1389,3 Gcal/h
Installed thermal capacity (including CCGT-223: 208.3 Gcal/h)
1933
Year of commissioning of CHPP-1
2020
Year of commissioning CCGT-223